Annual Report to shareholders
Released
Released
Announcement PDF
Annual Report
RareX Limited
2023
RareX HQ
Level 1, 338 Barker Rd
Subiaco WA 6008
Australia
P +61 8 6383 6593
info@rarex.com.au
ASX: REE
rarex.com.au
Table of Contents
Corporate Directory ..................................................................................................................................... 2
Review of Operations .................................................................................................................................. 3
Directors’ Report ....................................................................................................................................... 16
Auditor’s Independence Declaration ........................................................................................................ 30
Financial Statements ................................................................................................................................ 31
Auditor’s Report ......................................................................................................................................... 76
Mineral Resource Statement .................................................................................................................... 79
Schedule of Mining Tenements ............................................................................................................... 81
ASX Additional Information ...................................................................................................................... 82
1
Corporate Directory
DIRECTORS
LAWYERS
Mr Jeremy Robinson
Non-Executive Chairman
Hamilton Locke
Central Park, Level 48
152-158 St Georges Terrace
Perth, Western Australia 6000
Mr Danny Goeman
Non-Executive Director
Mr Shaun Hardcastle
Non-Executive Director
AUDITOR
Mr Cameron Henry
Non-Executive Director
SW Audit
Level 18, 197 St Georges Terrace
Perth, Western Australia 6000
Mr John Young
Non-Executive Director
SHARE REGISTRY
CHIEF EXECUTIVE OFFICER
Automic Registry Services
Level 2, 267 St Georges Terrace
Perth, Western Australia 6000
Mr James Durrant
Telephone: 1300 288 664
COMPANY SECRETARY
Ms Oonagh Malone
ASX CODES: REE, REEO
REGISTERED OFFICE & PRINCIPAL PLACE
OF BUSINESS
Level1, 338 Barker Road
Subiaco, Western Australia 6008
Telephone:
(08) 6383 6593
Website: www.rarex.com.au
2
Review of Operations
The Board of RareX Limited (RareX) is pleased to provide a review of operations across the
Company’s asset portfolio for the 2023 financial year and to date.
CEO’s Statement
”FY2023 has been a productive year for RareX, with the delivery of a significantly increased Mineral
Resource Estimate for our flagship Cummins Range Rare Earths & Phosphate Project and an evolution
in our planned development pathway for this unique critical minerals project towards a staged, threephase development approach. We’ve expanded our management and governance team to build a senior
leadership team that is highly relevant to the business and its transition towards operations, and we’ve
established RareXploration to curate a portfolio of synergistic assets with exciting exploration potential.
Our regional presence in the Kimberley is becoming more established as we work with local businesses,
community members and government in the region, and our positive relationship with the Jaru
Traditional Owners has continued to strengthen.
“Whilst these efforts are not yet reflected in our share price performance – in a large part due to
macroeconomic factors that are impacting many companies across the junior resources sector – I am
confident we have the fundamentals in place for robust growth: We hold the largest undeveloped rare
earths deposit in Australia and we’ve developed a low risk, low capital intensity strategy for its
development. Our metallurgical pathway is well defined, with first product samples now becoming
available for customer feedback, and we’re seeing positive signs of a recovery in rare earth pricing
alongside continued strong phosphate prices. The supply of phosphate and rare earths from reliable
supply chains is becoming increasingly sought-after, particularly by automotive manufactures where rare
earths feed the magnet motors and high-purity phosphate (such as ours) is fed into Lithium-IronPhosphate (LFP) battery technology. These exceptional foundations, coupled with exciting upcoming
work programs within our RareXploration initiative, should see improved sentiment in the near term.
“I would like to acknowledge the hard work and commitment of the small, but highly skilled RareX team
for their efforts over the year and would also like to thank all our shareholders for their continued
support.”
James Durrant
CEO
Watch our CEO summarise the year on the Investor Hub
3
Cummins Range Rare Earths & Phosphate Project
RareX’s flagship, 100%-owned Cummins Range Project is a nationally significant rare earths and
phosphate project located in the Kimberley region of Western Australia, 135km southeast of the town
of Halls Creek. Halls Creek is well provisioned for infrastructure with power, water and a sealed
airstrip. The Cummins Range Project is serviced by the Great Northern Highway which connects to
the Port of Wyndham.
Mineral Resource Update
RareX reported a substantial increase in the Mineral Resource Estimate (MRE) for the Cummins
Range Project during the reporting period.
The update, which was released in two stages for the Rare Dyke and Phos Dyke, delivered a total
Indicated and Inferred Mineral Resource of 519Mt at 0.32% TREO (total rare earths oxide) and 4.6%
P2O5 (phosphate) with appreciable quantities of niobium and scandium.
The amount of contained TREO is 1.6Mt with 360Kt of contained NdPr oxide. This MRE makes
Cummins Range the second-largest rare earths deposit, and the largest undeveloped rare earths
deposit, in Australia.
Within the large phosphate resource are significant tonnes of high-grade TREO including 52Mt at
1.02% TREO from a 0.6% cut-off. This accounts for one-third of the total contained TREO for the MRE
and shows there are significant tonnages of high-grade rare earth veins within the phosphate
Resource.
Table 1. Cummins Range Mineral Resource Estimate, P2O5 ≥2.5%
RARE DYKE
Classification
Tonnes
(Mt)
P2O5
(%)
TREO +
Y2O3 (ppm)
HREO
(ppm)
Nd2O3
(ppm)
Pr6O11
(ppm)
Nb2O5
(ppm)
Sc2O3
(ppm)
ThU
(ppm)
Indicated
45.9
6.2
5700
290
910
270
1000
90
90
Inferred
368.9
4.0
3030
160
490
150
570
60
40
Total
414.8
4.2
3320
180
540
160
620
70
50
PHOS DYKE
Classification
Tonnes
(Mt)
P2O5
(%)
TREO +
Y2O3 (ppm)
HREO
(ppm)
Nd2O3
(ppm)
Pr6O11
(ppm)
Nb2O5
(ppm)
Sc2O3
(ppm)
ThU
(ppm)
Indicated
20.8
8.0
3580
300
720
190
470
80
100
Inferred
83.8
5.4
2340
200
470
120
450
60
60
Total
104.6
5.9
2590
220
520
140
450
70
70
COMBINED
Classification
Tonnes
(Mt)
P2O5
(%)
TREO +
Y2O3 (ppm)
HREO
(ppm)
Nd2O3
(ppm)
Pr6O11
(ppm)
Nb2O5
(ppm)
Sc2O3
(ppm)
ThU
(ppm)
Indicated
66.6
6.8
5010
290
850
250
830
90
90
Inferred
452.7
4.2
2900
170
490
140
550
60
40
Total
519.3
4.6
3170
190
540
160
580
70
50
Notes:
1.
Due to effects of rounding, the total may not represent the sum of all components.
2.
TREO (ppm) includes: Light Rare Earth Oxides (LREO): La2O3, CeO2, Pr6O11, Nd2O3; and Heavy Rare Oxides (HREO): Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3,
Ho2O3, Er2O3, Tm2O3, Yb2O3, Lu2O3; + Y2O3
3.
ThU comprises ThO2 + U3O8 (ppm)
4.
Mineral Resource is reported from all blocks, classified as either Indicated or Inferred, where interpolated block grade is >2.5%P2O5
4
The relatively high NdPr and HREO (heavy rare earth oxide) content at Cummins Range is consistent
with that of monazite dominant mineralisation, resulting in an attractive Basket Price of US$34.20/kg
for the Project as shown below:
Table 2. Mineral Resource-Based Basket Price
Element
LREO
La2O3
CeO2
Pr6O11
Nd2O3
Sub-Total
HREO
Sm2O3
Eu2O3
Gd2O3
Tb4O7
Dy2O3
Ho2O3
Er2O3
Tm2O3
Yb2O3
Lu2O3
Y2O3
Sub-Total
Total Basket Price
US$/kg
Price US$/kg
% of TREO
Basket Price
US$/Kg
% of Basket Price
1.1
1.1
110.0
110.0
24.1%
45.5%
4.9%
16.9%
91.4%
0.3
0.5
5.4
18.6
24.7
0.8%
1.5%
15.8%
54.3%
72.4%
2.5
26.0
36.0
2,300.0
595.0
10.0
2.4%
0.6%
1.5%
0.2%
0.8%
0.1%
0.2%
0.02%
0.1%
0.02%
2.7%
8.6%
0.1
0.2
0.5
3.9
4.5
0.3
9.4
0.2%
0.4%
1.6%
11.4%
13.2%
0.0%
0.0%
0.0%
0.0%
0.0%
0.8%
27.6%
34.2
The Rare Dyke and Phos Dyke MRE includes 67Mt at 0.5% TREO and 7% P2O5 in the higher-confidence
Indicated category, which is mostly contained in the upper 100m. Importantly, the concentration of
the high value metals Neodymium and Praseodymium is 73kt.
A phosphate cut-off was chosen for the MRE as it better represents the geology and economic
potential of the deposit in that it captures the phosphate and almost all of the rare earths.
Full details of the Cummins Range MRE were provided in the Company’s ASX announcements dated
30 March and 1 May 2023.
Revised Development Strategy
Exploration and resource development programs undertaken throughout FY2023 re-framed the
Cummins Range Project as a highly significant phosphate-hosted rare earths deposit commencing
from surface.
This new understanding of the resource, coupled with metallurgical testwork undertaken during the
reporting period (see below), suggested the option for an initial fast-tracked DSO (direct shipping ore)
phosphate fertiliser phase (Stage 1), followed by phosphate-RE beneficiation (Stage 2) and
subsequently beneficiation from the underlying fresh rock and potential value chain development
(Stage 3).
5
This staged approach is expected to lower the risk associated with building the full rare earth value
chain outright at the beginning, by delivering a simpler and lower-cost DSO phosphate operation using
existing infrastructure, whilst maintaining development towards a large scale, strategic, rare earth and
phosphate critical minerals project.
Feasibility studies commenced during FY2023 to investigate this pathway, with a specific emphasis
on accelerating the DSO phase while maintaining a technical pathway towards the ultimate goal of
producing rare earth critical metals.
Enhanced Scoping Study
Subsequent to the end of the reporting period, RareX delivered an enhanced Scoping Study for
Cummins Range as a DSO start-up, 3-stage phosphate-enabled rare earth critical minerals project.
The enhanced Scoping Study built upon learnings and recommendations from an earlier Scoping
Study completed in September 2022, metallurgical testwork and the 2023 updated Mineral Resource
Estimate (outlined above). The Study’s main contributors were Primero, Mining Plus, Ausenco,
Shawmac and MBS Environmental.
Cautionary Statement
The Scoping Study referred to in this report was completed to determine the viability of a combined mine, DSO
operation and regolith beneficiation processing plant, under a staged development approach, in the East
Kimberly region of Western Australia, using phosphate and rare earth deposits at Cummins Range to produce
phosphate and rare earth concentrate products. It is a preliminary technical and economic study of the potential
viability of the Project. This Scoping Study is an order of magnitude technical and economical assessment and
is supported by Indicated and Inferred Mineral Resources 1.
The Study is based on the material assumptions outlined below. These include assumptions about the
availability of funding. While RareX considers all the material assumptions to be based on reasonable grounds,
there is no certainty that they will prove to be correct or that the range of outcomes indicated by the Study will
be achieved. To achieve the range of outcomes indicated in the Study, initial funding of approximately A$45M
will likely be required for Stage 1 followed by A$304M for Stage 2 and A$63M for Stage 3. Investors should note
that there is no certainty that RareX will be able to raise that amount of funding when needed. It is also possible
that such funding may only be available on terms that may be dilutive or otherwise affect the value of RareX’s
existing shares. It is also possible that RareX could pursue other value realisation strategies such as a sale,
partial sale or joint venture of the Project. If it does, this could materially reduce RareX’s proportionate ownership
of the Project.
The Study includes appropriate assessment of realistically assumed modifying factors together with other
relevant operational factors. The production target disclosed in the Study is underpinned by ore feed
classifications of 73% Indicated Resources and 27% Inferred. There is a low level of geological confidence
associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in
the determination of Indicated Mineral Resources or that the production target itself will be realised. The Study
demonstrates a potentially viable project and has given the Board of RareX the confidence to approve the
commencement of a Definitive Feasibility Study (DFS) for Stage 1 and Pre-Feasibility Study (PFS) for Stage 2
which will commence in Q3 2023. Additionally, the Board supports the on-going environmental baseline studies
and the finalisation of Native Title Agreement negotiations.
1 ASX Announcement 1 May 2023: Cummins Range Resource Soars to 519Mt 0.32% TREO, 4.6% P O . The Company confirms that it is
2 5
not aware of any new information or data that materially affects the information included in that announcement and that all material
assumptions and technical parameters underpinning the estimates in that announcement continue to apply and have not materially
changed.
6
The project concept outlined in the Scoping Study comprises:
Stage 1: Low CAPEX (A$45M), direct shipping ore (DSO), direct application (DA), high-bioavailability,
organic rock phosphate fertiliser for agricultural purposes. A production rate of up to 300ktpa of 23%
P2O5 is forecast for a period of 3 years.
Stage 2: Installation of a mid-sized beneficiation plant of A$304M to produce 550ktpa phosphate-rare
earth mineral concentrate from the weathered resource for the phosphoric acid and rare-earth
concentrate market.
Stage 3: A$63M upgrade of the Stage 2 plant in year 13 to produce a concentrate from the unweathered, fresh, rock below c.130m RL.
This staged development approach has the benefits of initiating early cashflows, building confidence
with the regulators on environmental management, furthering community relationships and social
performance, providing greater mineral resource definition, allowing bulk samples for metallurgy and
piloting, and establishing a functioning supply chain; all of which substantially de-risk Stage 2 which
transitions the project into a rare-earth critical mineral mine.
Key project metrics are presented in the table below.
Table 3: Enhanced Scoping Study Results Summary
Key project metrics
Physicals
Product type
Av. prod. rate (dry) (ktpa)
Average grade (%)
Duration (yr)
Costs
CAPEX (A$M)
OPEX (A$M/a)
OPEX (A$/t product)
Total SUSCAP (A$M/a)
Closure (A$M)
Products
Average TREO production (ktpa)
Average P2O5 production (ktpa)
Product price (A$/t)
Financial outcomes
Payback (pre-tax) (yr)
Average EBITDA LOM (A$M/a)
Total EBITDA (A$M)
Government tax (30%) (A$M)
Government royalty (A$M)
Native title contributions (A$M)
NPV8 (pre-tax / post-tax) (A$M)
IRR (pre-tax / post-tax) (%)
Notes:
•
•
Stage 1
DSO
270
23% P2O5
3
Stage 2
Phos-RE Con
503
33% P2O5; 2.3% TREO
10
Stage 3
Phos-RE Con
480
32% P2O5; 1.6% TREO
5
45
35
122
1
-
304
139
259
7
-
63
171
328
8
41
63
254
12
169
553
7
156
468
1.65
1.41
81
1,450
406
205
84
549 / 333
39% / 27%
1.69
Government royalties: 7.5% DSO, 5% Con
Native title (NT) contributions per currently negotiated outcomes - note the agreement has not been executed
7
The production target disclosed in the Study is underpinned by ore feed classifications of 73%
Indicated Resources and 27% Inferred. There is a low level of geological confidence associated with
Inferred Mineral Resources and there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production target itself will be realised.
Full details of the Cummins Range Enhanced Scoping Study were provided in the Company’s ASX
announcement dated 22 August 2023.
Based on the positive outcomes of the Enhanced Scoping Study, the RareX Board has resolved to now
commence a Definitive Feasibility Study for the Stage 1 DSO phosphate operation and a Pre-Feasibility
Study for the Stage 2 phosphate concentrate operation.
Metallurgical testwork
Metallurgical test work programs continued throughout the reporting period. Following positive
results from a 2022 sighter testwork program 2, a bulk flotation program was carried out to assess if
similar, or better, flotation performance can be achieved at larger scale with the same simple flotation
circuit. The bulk flotation using larger float cells is a good intermittent step to simulate pilot testing
and to assess if similar flotation kinetics can be achieved.
The test was performed on the same regolith composite that were tested in the sighter program and
was undertaken at Auralia Metallurgy in Perth. Results were reported subsequent to the end of the
reporting period, with a summary of the flotation testwork results with comparison to the sighter float
results shown in Table 4.
Table 4: Flotation Results Summary
Bulk Float
Product
Rougher
Concentrate
Cleaner
Concentrate
FINAL
Head Grade
Grade
%
P2O5
Recovery
%
Grade
%
22.6
96.3
0.51
34.4
91.1
12.9
100
Sighter Float1
TREO
Recovery
%
Grade
%
P2O5
Recovery
%
Grade
%
TREO
Recovery
%
81.7
23.8
94.3
0.55
79.1
0.72
70.7
34.1
85.7
0.70
63.9
0.33
100
12.9
100
0.33
100
As shown, excellent results were achieved from the bulk flotation test producing a phosphate
concentrate of 34.4% aligning to the sigher float performance. The bulk float P2O5 recovery of 91.1%
was also encouraging and was better that the sighter program.
The flotation tests were not focused on concentrating rare earths and the TREO head grade is
relatively low for this composite, however, the recovery trend of the rare earth showed high similarities,
albeit slightly lower recoveries, to the phosphate (as shown in Figure 1) for this composite. This is in
line with expectations and further supports the Scoping Study 3 assumptions for the product
recoveries and the production of a combined concentrate of apatite and monazite.
2 ASX announcement 04 October 2022: Met Testwork Delivers Premium Phosphate Concentrate
3
ASX announcement 22 Aug 2023: Enhanced Scoping Study for Cummins Range
8
100
%REO Recovery
90
80
70
60
50
40
30
20
20
30
40
50
60
70
80
90
100
% P2O5 Recovery
AM204-1 - CRCS4a Phosphate Bulk Float
AM134-3 - CRCS4a Phosphate Float
Figure 1: TREO recovery vs. P2O5 recovery
The bulk float results have further demonstrated the potential of producing a premium phosphaterare earth mineral concentrate from the Cummins Range deposit using a simple, proven beneficiation
technique.
Phosphate Bioavailability Testwork
Testwork on samples from Cummins Range confirmed the strong potential of the Direct Shipping Ore
(DSO) phosphate product to be used as direct-application agricultural fertiliser.
88 samples were selected from the two main geological units, the Rare Dyke (RD) and the Phos Dyke
(PD). The samples were selected to ensure broad coverage of different P2O5 grades, locations within
the orebody, and different weathering profiles. The testwork program comprised industry-standard
2% citric acid leach test and was conducted at LabWest Mineral Analysis.
The phosphorus bioavailability results were compared with industry “high” standard for the citric acid
method and are shown in Figure 2 and Figure 3 for Rare Dyke and Phos Dyke respectively. As
indicated, the majority of the 88 samples were shown to have very high phosphorus bioavailability
which was 2-4 times the industry high standard (>9.4% P2O5 dissolution in 2% citric acid). Good
bioavailability is also observed across all grades and weathering zones revealing potential for
increased production volumes.
These exceptional results demonstrate the potential of Cummins Range DSO material for use as
direct application fertilisers.
9
Figure 2: Phosphorous Bioavailability Results vs. Industry Standard - Rare Dyke
Figure 3: Phosphorous Bioavailability Results vs. Industry Standard - Phos Dyke
Note: CW – Completely Weathered; SW – Strongly Weathered; MW – Moderately Weathered, WW –
Weakly Weathered; FR – Fresh
10
The Cummins Range Resource is an igneous deposit which means the rocks are naturally lower in
impurities and deleterious elements when compared with sedimentary rocks. The results from the 88
samples confirm very low levels of deleterious elements including fluorine (F), chlorine (Cl), cadmium
(Cd) and lead (Pb) which are well below industry limits as shown in Table 5.
Table 5: Deleterious Elements Results Summary
Deleterious
Element
Unit
Assay Range
Average Level
Industry Limit for
Phosphorus
Fertilisers 4
F
%
0.18 - 4.00
1.02
<4
Cl
%
0.01 - 0.11
0.03
<2
Cd
mg/kg P
3.31 - 137.64
32.82
<300
Pb
mg/kg
1.70 – 208.00
24.32
<500
Following the positive results, additional formic acid and water leach tests are planned to further
assess the phosphorus bioavailability of the potential DSO material. RareX has appointed a fertiliser
consultant to leverage current and future DSO testwork results, assist with better understanding of
the agronomic effects of the Cummins Range DSO material and support the development of product
marketing and offtake agreements.
In addition to the DSO analysis, phosphate mineral beneficiation studies for both the Rare Dyke and
Phos Dyke materials are underway, with the rare earth deportment also being studied. Phosphateoptimised beneficiation is a strong alternative to rare earth-optimised flotation and may deliver
greater value realisation from the Cummins Range Resource.
Geotechnical Assessment
Geotechnical tests were performed on diamond core from along a near surface high-grade zone
within the orebody to provide some high-case strength parameters of the rocks to be mined.
Note that for near-surface material in the weathered zone of the deposit, core at Cummins Range is
quite friable and as such most core is not suitable for strength testing at the lab; therefore, core
sections that are sufficiently coherent for lab testing are representing a rock strength high-case for
processing feed. Sections of phoscorite and ultramafic sample that were sufficiently coherent were
tested at E-Precision Laboratory, Perth.
Results returned UCS values in the range of 70 MPa for the phoscorite samples, which are the likely
higher grade ore feed for the Project. The ultramafic sample failed at 22 MPa, albeit a microfracture
appears to be the release mechanism in this case not the rock mass. This warrants further testing as
part of a broader geotechnical campaign, required for detailed designs and approvals which seeks to
assess slope mechanics as well as ore parameters.
The comparatively low rock strength within the pit shell presents an opportunity towards reduced
operating costs via surface-mining, thus eliminating drill and blast operating operations. RareX has
reached out to potential providers of surface miners and surface mining services to establish the
viability of this operational pathway. Surface miners could provide further upside to mining and
4
Industry limit as stated in “National Code of Practice for Fertilizer Description and Labelling”, Fertiliser Australia 2018
11
processing costs through pre-screening and crushing of ore in-situ and reduce environmental impacts
common with regards to blasting operations.
MoU with OrdCo
RareX signed a collaboration Memorandum of Understanding (MoU) with Ord River District Cooperative Ltd (OrdCo) during the reporting period to develop a phosphate product roadmap to support
the Kununurra agricultural sector with a portion of Cummins Range’s phosphate product mix.
OrdCo, which has been in operation since 1963, is the leading independent agricultural co-operative
based in the Ord River Irrigation Area (ORIA) and provides a complete range of farming inputs and
services to the local region and greater surrounds.
The east Kimberley is the largest producer of irrigated horticulture in the region, powered by the Ord
Irrigation Scheme as water from Lake Argyle and Lake Kununurra is diverted and gravity fed through
kilometres of open channels to irrigate farmlands. In the process, sustainable hydroelectricity is
produced to power the east Kimberley.
The ORIA has expanded from a historical base of around 15,000 ha to approximately 21,000 ha.
Developments that will bring the area to 28,000 ha are underway with the potential to increase to
60,000 ha or more. Outside the ORIA, value add developments on many stations, such as dryland
cropping using wet season rainfall, are now resulting in significant cropping areas. This means the
total area of intensive agriculture and therefore demand for fertilisers is increasing quickly across the
region.
Under the terms of the MoU, the parties agreed to discuss and negotiate the terms of a binding offtake agreement and distribution agreement, and to jointly develop a product roadmap for the
phosphate products to be produced from the Cummins Range Project. This work is ongoing with crop
trials being initiated.
The MoU also contemplates undertaking studies to evaluate the potential to capture carbon credits
as part of general R&D-based activities.
Heritage and Environmental Update
Flora and fauna surveys for both the dry and wet seasons were completed during the June 2023
Quarter in line with Federal and State regulatory guidance, with strong input on ecological cultural
values from the Jaru people, the Traditional Owners of the land on which the Project is located.
Information collected during the field surveys is now being compiled and analysed, with preliminary
observations consistent with expectations of floral and faunal assemblages for the project area.
The results of the survey will be used to inform regulatory approvals and drive the development of an
environmental management plan for the project. The management plan will ensure that any future
mining activities are undertaken in a way that minimise the impact on the environment.
The survey results and study outcomes will be used to develop a project description with the relevant
information to engage the regulator for pre-referral discussions. The Company believes that by
focussing approvals on the above water table portion of the resource, demonstrating a relatively low
impact project and by developing robust environmental and cultural management plans, approvals
can be secured through the Environmental Protection Authority (EPA) at State level. If the Project is
deemed high impact, it will be referred for federal review through the Department of Climate Change,
Energy, the Environment and Water (DCCEEW).
12
Negotiations with the Jaru Traditional Owners are on track with a draft Mining Agreement and
compensation proposal complete. The RareX team, with support from Allens law firm, will continue
to meet with the Traditional Owners Negotiation Committee (TONC) and the PBC board with the goal
of completing negotiations before the start of the 2023 wet-season.
RareX thanks the Jaru TONC for a constructive, collaborative, and pragmatic approach to the
negotiations.
Exploration
Drilling and exploration programs were undertaken throughout the reporting period aimed at infilling
and extending the Cummins Range Mineral Resource Estimate (MRE). Results from these programs
fed into the MRE updates announced for the Rare Dyke and Phos Dyke, announced on 30 March and
1 May 2023 respectively.
A new program of diamond drilling commenced at Cummins Range late in the reporting period.
The program was undertaken by Kalgoorlie-based drilling company, Kal Drill, and comprised PQ
drilling targeting the Indicated portion of the Mineral Resource within both the Rare and Phos Dykes,
which totals 67Mt at 0.5% TREO and 7% P2O5.
The drilling program supports all three proposed stages of the Cummins Range development
roadmap (see ASX announcement 13 April 2023).
A program of reverse circulation (RC) drilling by Stark Drilling was completed at Cummins Range in
August 2023, focused on infilling and upgrading the shallow high-grade phosphate DSO Resource to
support the Stage 1 DSO phosphate operation.
Non-core Projects
RareXploration is the internal division of the Company which focusses on the non-core projects of
RareX including investments and tenement holdings.
RareX holds material ownership in 3 listed companies: Kincora Copper (ASX:KCC), Cosmos
exploration (ASX:C1X) and Canada Rare Earths Corporation (LL.V). During the reporting period, RareX
agreed to adjust its interest in KCC from project level to corporate level. This transaction is expected
to complete later in the year.
New South Wales Gold Projects
Throughout the reporting period, RareX held a 35% free-carried interest in six tenements in joint
venture with Kincora Copper Limited (ASX: KCC). The tenements are located in Australia’s foremost
porphyry region in the Lachlan Fold Belt, NSW, and include the Trundle, Fairholme, Jemalong,
Cundumbul and Condobolin Projects.
In addition to its 35% asset level interest, RareX also held 3% of Kincora Copper shares.
Weld North
A lithogeochemical soil survey was completed over the Weld North Project. Soil samples were taken
on a 1km grid. Assay results were still awaited at the end of the reporting period, with results to be
used to create a geochemical assessment of lithologies and identify potential anomalies.
13
Hong Kong Project
No work was undertaken during the reporting period and the Hong Kong tenement E47/3566 was
relinquished during the June 2023 Quarter. The gold tenement was plainted and, following
Share your feedback
Discover